• Weather Dek2 Fast-Fix has been specifically designed by Puhos for use in conjunction with engineered floor beams

• 18mm Weather Dek2 panels should be used over 400mm spacing and 22mm panels over 600mm spacing in domestic loading condiditons

• Take special care when handling plot lot deliveries as they may not feature site proof packaging, as do larger ex works pallets

• Follow basic practice concerning site handling, expansion gaps and laying instructions as outlined above

• Floor beams should be secured and braced before starting to lay Weather Dek2 boards. Any standing water on surface flanges should be wiped down

• Use the Weather Dek 2 application gun to apply a 6mm x 6mm bead of Weather Dek2 Fast-Fix bonding adhesive centrally to the face of the upper flange, in 600mm lengths, for the first run of boards

• Fix the boards within 30 minutes of the bonding adhesive being applied to the flange. Do not drag boards excessively during fixing

• Lay the tongued and grooved Weather Dek boards with long edges at right angles to the beams. The short edges must fall centrally on a beam flange, should not cantilever and must be supported around the perimeter

• Glue all tongued and grooved edges with an ample bead of Weather Dek2 adhesive applied to the grooved edge and a smaller bead applied to the top edge of the tongue. This is an important procedure when boards are used in exterior locations.

• The first run of boarding should be in place and square. One 55 mm Weather Dek2 annular ring shank nail should be fixed 50mm from the perimeter edge. Hold the boards in place by secret nailing, twice per board, through the tongue of the long edge at a 20 degree angle. This also avoids board movement when further rows are fixed

• Fix the second and subsequent rows of boarding using the same method as above except that nailing through the board face is unnecessary. Only secret nailing through the tongue of the long edge, twice per board, is required. On the last row of boarding, one 55mm Weather Dek2 annular ring shank nail per beam should again be fixed 50 mm from the perimeter edge.

• After fixing the first two rows of Weather Dek2 Fast-Fix, tape all board edges and perimeter edges using only Weather Dek2 high performance tape. Repeat the taping procedure after fixing every further two rows of boards.
• Floors should be left to cure for a minimum of 24 hours prior to use as a walkway

• Do not leave the tape fixing operation until the floor area is complete

• Ensure the tape is applied in clean, dry conditions. Always use the Weather Dek2 tape roller applicator and ensure all tape is fully bonded to the board surface. Tape should be folded over exposed perimeter board edges prior to fixing the boards

• Avoid overloading the floor deck with construction materials and avoid standing packs of bricks or blocks on the deck

• Follow these instructions to ensure correct fitting of the floor and Weather Dek2 Fast-Fix will provide a high quality floor with a pristine surface that is extremely quiet and durable.