Always use boards with a protected surface such as Dek Shield and Weather Dek to help avoid board cupping Ensure the concrete sub-floor is dry and has a 1000g polythene vapour check taped and sealed directly on the surface of the sub-floor, make sure this is not punctured by concrete nibs etc. The polythene should be taken up behind the skirting boards Place a minimum 25mm insulation layer, preferably extruded polystyrene on top of the vapour check ensuring joints do not correspond with the chipboard Lay boards directly from the pack. Do not let them pick up moisture prior to laying Remember the expansion gaps Glue all board edges with a liberal quantity of D3 PVA Keep boards as dry and clean as possible during the construction period Correct site conditions and product application is vital when fixing floating floors. If wood based flooring is used in hostile conditions distortion may occur. |
|